4 active projects totaling 696.6 MW in the MISO queue, plus 9 with terminal status (shown grayed).

4active projects
696.6active MW
13total filed
Queue IDProjectkVMWResourceStatus
J2174 Not reported 230 390 Solar Withdrawn
J3261 Not reported 230 200 Solar Withdrawn
J866 Not reported 230 200 Wind Active
J2571 Not reported n/r 176.6 Wind Active
J1440 Not reported 115 160 Solar Active
J3175 Not reported 230 160 Solar Active
J2432 Not reported 115 150 Solar Withdrawn
J2857 Not reported 115 150 Hybrid Withdrawn
J2939 Not reported 115 150 Solar Withdrawn
J2015 Not reported n/r 90 Battery Withdrawn
J3177 Not reported 230 80 Battery Withdrawn
J1287 Not reported 115 50 Solar Withdrawn
J1439 Not reported 115 40 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first