Substation Scout

MISO request J866

MISO queue ID J866

Queue request J866 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW wind project in Tunica County, MS, according to Berkeley Lab’s queue data file. The filing names Batesville - Robert E. Ritchie line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of July 1, 2021.

Queue IDJ866
Project nameNot reported
Status (as published)Active
SubstationBatesville - Robert E. Ritchie line
Point of interconnectionBatesville - Robert E. Ritchie 230 kV line
CountyTunica
StateMS
Voltage230 kV
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2021-07-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Tunica, MS: 13 requests in the MISO queue, 4 active totaling 696.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityEntergy
ClusterDPP-2017-AUG South
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Under Construction
Queue date2017-06-16
Interconnection agreement date2020-04-06
Operational date2024-04-19

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.