7 active projects totaling 1,409 MW in the MISO queue, plus 11 with terminal status (shown grayed).

7active projects
1,409active MW
18total filed
Queue IDProjectkVMWResourceStatus
J3640 Not reported 345 300 Wind Withdrawn
J3865 Not reported 138 250 Wind Active
J796 Not reported 138 239 Solar Operational
J3864 Not reported 345 230 Wind Active
J195 Not reported 138 200 Wind Withdrawn
J2672 Not reported 138 200 Solar Active
J602 Not reported 138 200 Wind Withdrawn
J187 Not reported 138 198 Wind Withdrawn
J1089 Not reported 138 170 Solar Withdrawn
J1297 Not reported 138 170 Solar Active
R5063 Replacing 160 MW of Solar with 80 MW of Solar and 90 MW of BESS; Bell Solar 138 170 Hybrid Active
J1088 Not reported 138 150 Solar Withdrawn
J1394 Not reported 138 150 Solar Withdrawn
J4122 Not reported n/r 150 Battery Active
J264 Not reported 138 120.8 Wind Withdrawn
J925 Not reported 138 50 Solar Withdrawn
S1038 Surplus; J796 138 50 Hybrid Withdrawn
G250 Not reported n/r 4 Other Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first