Substation Scout

Polk, TX interconnection queue

4 active projects totaling 725 MW in the MISO queue, plus 6 with terminal status (shown grayed).

4active projects
725active MW
10total filed
Queue IDProjectkVMWResourceStatus
J3985 Not reported n/r 240 Hybrid Active
J867 Not reported n/r 200 Solar Withdrawn
J2754 Not reported 138 170 Solar Active
J1442 Not reported 138 165 Solar Active
J1030 Not reported 138 150 Solar Operational
J1278 Not reported 138 100 Solar Withdrawn
J2242 Not reported n/r 100 Hybrid Withdrawn
J418 Not reported 138 100 Solar Withdrawn
J1962 Not reported 138 75 Solar Withdrawn
J1963 Not reported 138 25 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.