Substation Scout

MISO request J1442

MISO queue ID J1442

Queue request J1442 was listed in the MISO interconnection queue at the end of 2025 as a 165 MW solar project in Polk County, TX, according to Berkeley Lab’s queue data file. The filing names Rich (SHECO) - Livingston Line Tap as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of May 1, 2025.

Queue IDJ1442
Project nameNot reported
Status (as published)Active
SubstationRich (SHECO) - Livingston Line Tap
Point of interconnectionRich (SHECO) - Livingston 138 kV Line Tap
CountyPolk
StateTX
Voltage138 kV
Capacity165 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2025-05-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Polk, TX: 10 requests in the MISO queue, 4 active totaling 725 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY TEXAS, INC.
ClusterDPP-2019 South
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA Complete; Post GIA Status: Under Construction
Queue date2019-04-29
Interconnection agreement date2022-08-04

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first