Substation Scout

Phillips, AR interconnection queue

9 active projects totaling 1,390.5 MW in the MISO queue, plus 6 with terminal status (shown grayed).

9active projects
1,390.5active MW
15total filed
Queue IDProjectkVMWResourceStatus
J3802 Not reported 230 300 Solar Withdrawn
J4196 Not reported 115 300 Solar Active
J3270 Not reported 230 250 Solar Withdrawn
J3893 Not reported 230 214 Solar Withdrawn
J3116 Not reported 230 200 Hybrid Withdrawn
S1074 Surplus; J834 230 200 Hybrid Active
J2750 Not reported 230 197.5 Solar Active
J3292 Not reported 230 193 Wind Active
J3812 Not reported 161 158.6 Hybrid Withdrawn
J2456 Not reported 230 100 Hybrid Active
J3112 Not reported 115 100 Hybrid Active
J3141 Not reported 230 100 Solar Active
J663 Not reported 230 100 Solar Operational
J834 Not reported 230 100 Solar Operational
J3374 Not reported 230 65 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.