Dubois, IN interconnection queue

7 active projects totaling 610 MW in the MISO queue, plus 2 with terminal status (shown grayed).

7active projects
610active MW
9total filed
Queue IDProjectkVMWResourceStatus
J3550 Not reported 138 200 Battery Active
J1369 Not reported 138 100 Solar Active
J1391 Not reported 138 100 Solar Active
J1736 Not reported 138 100 Solar Active
J1707 Not reported 345 72 Solar Withdrawn
J2123 Not reported 138 50 Battery Withdrawn
S1026 Surplus; J1369 138 50 Hybrid Active
S1043 Surplus; J1369 138 50 Hybrid Active
J3208 Not reported n/r 10 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.