MISO request J3550
MISO queue ID J3550
Queue request J3550 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW battery project in Dubois County, IN, according to Berkeley Lab’s queue data file. The filing names Duff - Dubois as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 10, 2027.
| Queue ID | J3550 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Duff - Dubois |
| Point of interconnection | Duff - Dubois 138.0 kV |
| County | Dubois |
| State | IN |
| Voltage | 138 kV |
| Capacity | 200 MW |
| Resource (as published) | Battery |
| Resource category | Battery (normalized for filtering) |
| Proposed online date | 2027-09-10 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Dubois, IN: 9 requests in the MISO queue, 7 active totaling 610 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South |
|---|---|
| Cluster | DPP-2023 Central |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | In Progress (unknown study) |
| Study phase (as the queue printed it) | Study Phase: DPP 1 |
| Queue date | 2024-04-18 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.