Georgia Power's quarterly report to the Georgia Public Service Commission on the large loads in its economic development pipeline.

What this is

Georgia Power files a Large Load Economic Development Report with the Georgia Public Service Commission every quarter. The 2023 IRP Update stipulation (Docket 55378) requires it, and the 2025 IRP stipulation (Docket 56002) added the date each new project entered the pipeline and which new projects have signed a Contract for Electric Service. Each report comes with a spreadsheet: one row per large-load project, with its stage, announced load, segment, initial in-service date and a yearly load ramp to 2037.

The public version redacts each project's name, city, county and GPS coordinates. What is left is still unusual: a utility listing, project by project and quarter by quarter, how much large load is asking to connect and how far along each project is. This page has every public quarter on file, Q1 2024 through Q2 2026.

118projects, Q2 2026
80.1 GWannounced load, as filed
32 · 15.6 GWwith a Request or Contract for Electric Service
June 30, 2026as of; Q2 2026 report filed August 17, 2026

How changes are tracked here

Because the rows carry no name and no ID, there is no reliable way to tell that a 1,200 MW row this quarter is the same project as a 1,200 MW row last quarter. Matching them on size and dates would be a guess, so this page does not do it.

It does not need to. Each report includes Georgia Power's own lists of what changed since the previous quarter: projects added (with the date each entered the pipeline, from mid-2025 on), projects removed with the reason, restated loads, stage changes and in-service date changes. Those lists are reproduced here as filed.

They also add up. For every quarter from Q3 2024 on, last quarter's total, plus the projects added, minus the projects removed, plus the restated loads, equals this quarter's total, to the megawatt and to the project. The pipeline checks that on every refresh and refuses a quarter that does not add up. The first two public quarters cannot be checked this way, because their spreadsheets have no list of added projects.

What the data does not say

There is no location. A row says whether the project is inside or outside Georgia Power's service territory and nothing more, so no row can be placed near a site, a county or a substation.

Announced load is the load Georgia Power reports for a project as of 2037. Most rows are at the Technical Review stage, before any Request for Electric Service. Georgia Power's own reports count only projects that have executed a Request for Electric Service or a Contract for Electric Service as customer commitments, and this page uses the same line. A pipeline total is the sum of what projects have asked about, not a forecast of demand.

The segment column ("Data Center", "Manufacturing", "Clean Energy Tech") is Georgia Power's label, not this site's. Its wording changed between quarters ("Data Centers", "Data Center", "Data Center/Crypto"), and the labels are shown as filed rather than merged.

A removed project left the report; it did not necessarily stop. The reasons are Georgia Power's, quoted as filed. One of them ("See Note 1") says the project is still active but its load is now below the large-load threshold. A removal says nothing about what can now be connected anywhere.

What changed in Q2 2026

From Georgia Power's own lists, against Q1 2026: 11 projects added (6,776 MW), 6 removed from the report (1,382 MW), 6 with a restated load (net +1,535 MW), 1 stage change and 10 changes to an initial in-service date. These add up: 73,130 MW last quarter, plus 6,776 added, minus 1,382 removed, plus 1,535 restated, is 80,059 MW.

Added

Announced MWEntered the pipeline
1,500June 11, 2026
900June 30, 2026
880June 17, 2026
750May 1, 2026
700June 2, 2026
612June 30, 2026
534May 7, 2026
400May 11, 2026
200May 6, 2026
200June 30, 2026
100April 21, 2026

Removed from the report

Announced MW last quarterReason, as filed
450No Decision
405See Note 1
“Project still active but load now falls below the threshhold to be a large load customer”
252See Note 1
“Project still active but load now falls below the threshhold to be a large load customer”
180See Note 1
“Project still active but load now falls below the threshhold to be a large load customer”
50Site
45See Note 1
“Project still active but load now falls below the threshhold to be a large load customer”

Restated load

ChangeLast quarterThis quarter
+755 MW4811,236
+610 MW9101,520
+251 MW500751
+24 MW264288
+20 MW230250
−125 MW240115

Stage changes

FromTo
Technical ReviewRequest for Electric Service

A project removed from the report may still be active; the reason is Georgia Power's. A removal is not evidence that power can be connected anywhere.

Quarter by quarter

Every public quarter on file. Added, removed and restated are Georgia Power's own lists. "Adds up" means last quarter's total plus those lists equals this quarter's, to the megawatt and the project.

QuarterProjectsAnnouncedRequest or ContractAddedRemovedRestatedAdds up?Filing
Q2 202611880.1 GW32 · 15.6 GW11 · 6,776 MW6 · 1,382 MW+1,535 MWYesfiled August 17, 2026
Q1 202611373.1 GW31 · 12.4 GW13 · 12,626 MW6 · 2,850 MW−2,518 MWYesfiled May 15, 2026
Q4 202510665.9 GW29 · 11.8 GW22 · 23,035 MW23 · 7,281 MW−745 MWYesfiled March 4, 2026
revised filing; replaces the one filed February 11, 2026
Q3 202510750.9 GW28 · 11.0 GW13 · 6,780 MW24 · 14,345 MW+1,606 MWYesfiled March 4, 2026
revised filing; replaces the one filed November 21, 2025
Q2 202511856.8 GW26 · 8.8 GW11 · 5,990 MW8 · 1,636 MW+375 MWYesfiled August 15, 2025
Q1 202511552.1 GW26 · 8.3 GW19 · 10,571 MW8 · 2,291 MW−367 MWYesfiled May 22, 2025
Q4 202410444.2 GW26 · 8.3 GW18 · 12,203 MW4 · 1,698 MW−957 MWYesfiled February 21, 2025
Q3 20249034.6 GW25 · 8.0 GW30 · 14,737 MW10 · 3,002 MW+134 MWYesfiled November 18, 2024
Q2 20247022.8 GW24 · 7.3 GWnot listed10 · 2,595 MW−581 MWNot checkable*filed August 16, 2024
Q1 20246419.6 GW23 · 6.2 GWnot listed20 · 6,080 MW−204 MWFirst public quarterfiled May 15, 2024

* Q2 2024 has no list of added projects, so it cannot be checked against Q1 2024. To add up, it would need 16 added projects totaling 6,359 MW that Georgia Power did not itemize.

Projects in Q2 2026

All 118 rows, largest announced load first. Contract for Electric Service: 22 (9.6 GW) · Request for Electric Service: 10 (6.0 GW) · Technical Review: 86 (64.5 GW). Announced load is what Georgia Power reports for the project as of 2037, not a study result and not a commitment.

Announced MWStageSegment, as filedTerritoryInitial in-service
3,500Technical ReviewData Center/CryptoInsideQ2 2031
3,210Request for Electric ServiceData Center/CryptoInsideQ2 2028
3,000Technical ReviewData Center/CryptoOutsideQ4 2027
2,000Technical ReviewData Center/CryptoOutsideQ2 2028
2,000Technical ReviewData Center/CryptoOutsideQ2 2028
2,000Technical ReviewData Center/CryptoOutsideQ2 2028
1,600Technical ReviewData Center/CryptoInsideQ2 2030
1,520Technical ReviewData Center/CryptoInsideQ2 2028
1,500Technical ReviewData Center/CryptoInsideQ4 2027
1,500Technical ReviewData Center/CryptoOutsideQ2 2028
1,463Technical ReviewData Center/CryptoOutsideQ4 2027
1,429Contract for Electric ServiceData Center/CryptoOutsideQ2 2024
1,400Contract for Electric ServiceData Center/CryptoInsideQ4 2027
1,400Contract for Electric ServiceData Center/CryptoInsideQ2 2028
1,400Technical ReviewData Center/CryptoInsideQ2 2028
1,400Technical ReviewData Center/CryptoInsideQ2 2030
1,236Technical ReviewData Center/CryptoInsideQ2 2029
1,200Technical ReviewData Center/CryptoOutsideQ2 2028
1,200Technical ReviewData Center/CryptoInsideQ4 2027
1,200Technical ReviewData Center/CryptoInsideQ4 2027
1,200Technical ReviewData Center/CryptoInsideQ4 2027
1,200Technical ReviewData Center/CryptoInsideQ4 2027
1,200Technical ReviewData Center/CryptoInsideQ2 2028
1,115Technical ReviewData Center/CryptoOutsideQ2 2028
1,020Technical ReviewManufacturingMultiple SitesQ4 2027
1,000Technical ReviewData Center/CryptoInsideQ2 2028
910Technical ReviewData Center/CryptoInsideQ4 2027
910Technical ReviewData Center/CryptoInsideQ4 2027
901Contract for Electric ServiceData Center/CryptoInsideQ4 2027
900Technical ReviewData Center/CryptoInsideQ2 2029
880Technical ReviewData Center/CryptoInsideQ2 2029
860Technical ReviewData Center/CryptoInsideQ2 2029
840Technical ReviewData Center/CryptoInsideQ2 2029
800Contract for Electric ServiceData Center/CryptoInsideQ1 2027
751Technical ReviewData Center/CryptoInsideQ2 2029
750Technical ReviewData Center/CryptoInsideQ4 2027
750Technical ReviewData Center/CryptoOutsideQ2 2028
725Technical ReviewData Center/CryptoInsideQ4 2027
725Technical ReviewData Center/CryptoInsideQ4 2027
700Technical ReviewData Center/CryptoOutsideQ4 2027
693Request for Electric ServiceData Center/CryptoInsideQ2 2028
651Technical ReviewData Center/CryptoInsideQ2 2029
648Technical ReviewData Center/CryptoInsideQ2 2028
648Technical ReviewData Center/CryptoInsideQ4 2027
612Technical ReviewData Center/CryptoInsideQ4 2027
600Technical ReviewData Center/CryptoInsideQ2 2028
600Technical ReviewData Center/CryptoInsideQ4 2027
600Technical ReviewData Center/CryptoInsideQ4 2027
600Technical ReviewData Center/CryptoInsideQ4 2027
576Technical ReviewData Center/CryptoInsideQ4 2027
567Technical ReviewData Center/CryptoInsideQ2 2030
550Technical ReviewData Center/CryptoInsideQ4 2027
550Technical ReviewData Center/CryptoOutsideQ2 2030
550Technical ReviewData Center/CryptoInsideQ4 2027
534Technical ReviewData Center/CryptoInsideQ2 2028
523Contract for Electric ServiceData Center/CryptoOutsideQ4 2026
502Request for Electric ServiceData Center/CryptoInsideQ2 2028
500Technical ReviewData Center/CryptoInsideQ4 2027
500Technical ReviewData Center/CryptoInsideQ2 2030
500Technical ReviewManufacturingInsideQ4 2027
480Technical ReviewData Center/CryptoInsideQ4 2027
455Technical ReviewData Center/CryptoInsideQ4 2027
455Technical ReviewData Center/CryptoInsideQ2 2029
455Technical ReviewData Center/CryptoInsideQ4 2027
455Technical ReviewData Center/CryptoInsideQ4 2027
450Technical ReviewData Center/CryptoInsideQ4 2027
450Technical ReviewData Center/CryptoOutsideQ4 2027
432Request for Electric ServiceData Center/CryptoInsideQ2 2029
432Technical ReviewData Center/CryptoInsideQ4 2027
420Technical ReviewData Center/CryptoInsideQ2 2028
400Technical ReviewData Center/CryptoInsideQ4 2027
365Technical ReviewData Center/CryptoOutsideQ4 2027
365Technical ReviewData Center/CryptoInsideQ4 2027
360Technical ReviewData Center/CryptoOutsideQ4 2027
360Technical ReviewData Center/CryptoInsideQ2 2029
350Technical ReviewData Center/CryptoInsideQ4 2027
350Technical ReviewData Center/CryptoInsideQ2 2028
325Technical ReviewData Center/CryptoOutsideQ2 2028
324Contract for Electric ServiceData Center/CryptoInsideQ2 2026
311Contract for Electric ServiceData Center/CryptoInsideQ1 2026
300Request for Electric ServiceData Center/CryptoInsideQ2 2028
300Technical ReviewData Center/CryptoInsideQ2 2028
300Technical ReviewData Center/CryptoInsideQ4 2027
288Technical ReviewData Center/CryptoInsideQ2 2029
250Technical ReviewData Center/CryptoInsideQ2 2029
250Technical ReviewData Center/CryptoOutsideQ4 2027
240Contract for Electric ServiceData Center/CryptoInsideQ1 2025
240Contract for Electric ServiceData Center/CryptoOutsideQ4 2025
240Technical ReviewData Center/CryptoInsideQ4 2027
233Request for Electric ServiceData Center/CryptoInsideQ2 2030
225Request for Electric ServiceData Center/CryptoInsideQ2 2028
216Contract for Electric ServiceData Center/CryptoInsideQ1 2028
216Contract for Electric ServiceData Center/CryptoInsideQ3 2025
216Request for Electric ServiceData Center/CryptoInsideQ2 2030
216Technical ReviewData Center/CryptoInsideQ2 2029
216Technical ReviewData Center/CryptoInsideQ2 2029
207Contract for Electric ServiceClean Energy TechOutsideQ4 2025
200Technical ReviewData Center/CryptoOutsideQ4 2027
200Technical ReviewData Center/CryptoInsideQ4 2027
200Technical ReviewData Center/CryptoOutsideQ4 2027
200Technical ReviewData Center/CryptoInsideQ4 2027
192Contract for Electric ServiceData Center/CryptoOutsideQ1 2024
182Contract for Electric ServiceData Center/CryptoInsideQ2 2026
180Contract for Electric ServiceData Center/CryptoOutsideQ1 2026
180Contract for Electric ServiceData Center/CryptoInsideQ4 2026
180Technical ReviewData Center/CryptoInsideQ2 2029
175Technical ReviewData Center/CryptoInsideQ2 2028
150Contract for Electric ServiceData Center/CryptoInsideQ4 2024
145Contract for Electric ServiceData Center/CryptoInsideQ4 2028
144Technical ReviewData Center/CryptoOutsideQ2 2029
126Contract for Electric ServiceClean Energy TechInsideQ4 2025
120Contract for Electric ServiceData Center/CryptoInsideQ3 2026
115Technical ReviewClean Energy TechInsideQ4 2027
105Request for Electric ServiceManufacturingInsideQ4 2027
100Technical ReviewManufacturingEconomic DevelopmentQ2 2030
90Contract for Electric ServiceClean Energy TechInsideQ4 2025
79Request for Electric ServiceManufacturingOutsideQ4 2027
50Technical ReviewManufacturingInsideQ2 2030

Source

Georgia Power Company, Quarterly Large Load Economic Development Report, public-disclosure attachment, Georgia Public Service Commission Docket 55378 (the reports also cite Docket 56002). Q2 2026 report filed August 17, 2026; workbook PD Large Load Economic Development Report Q2 2026.xlsx. Retrieved 2026-10-24; exported 2026-11-23.

More

Large Load Registry, all sources → · Queue Wire — generation queue deltas → · Roadmap →

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first