Georgia Power's quarterly report to the Georgia Public Service Commission on the large loads in its economic development pipeline.
What this is
Georgia Power files a Large Load Economic Development Report with the Georgia Public Service Commission every quarter. The 2023 IRP Update stipulation (Docket 55378) requires it, and the 2025 IRP stipulation (Docket 56002) added the date each new project entered the pipeline and which new projects have signed a Contract for Electric Service. Each report comes with a spreadsheet: one row per large-load project, with its stage, announced load, segment, initial in-service date and a yearly load ramp to 2037.
The public version redacts each project's name, city, county and GPS coordinates. What is left is still unusual: a utility listing, project by project and quarter by quarter, how much large load is asking to connect and how far along each project is. This page has every public quarter on file, Q1 2024 through Q2 2026.
How changes are tracked here
Because the rows carry no name and no ID, there is no reliable way to tell that a 1,200 MW row this quarter is the same project as a 1,200 MW row last quarter. Matching them on size and dates would be a guess, so this page does not do it.
It does not need to. Each report includes Georgia Power's own lists of what changed since the previous quarter: projects added (with the date each entered the pipeline, from mid-2025 on), projects removed with the reason, restated loads, stage changes and in-service date changes. Those lists are reproduced here as filed.
They also add up. For every quarter from Q3 2024 on, last quarter's total, plus the projects added, minus the projects removed, plus the restated loads, equals this quarter's total, to the megawatt and to the project. The pipeline checks that on every refresh and refuses a quarter that does not add up. The first two public quarters cannot be checked this way, because their spreadsheets have no list of added projects.
What the data does not say
There is no location. A row says whether the project is inside or outside Georgia Power's service territory and nothing more, so no row can be placed near a site, a county or a substation.
Announced load is the load Georgia Power reports for a project as of 2037. Most rows are at the Technical Review stage, before any Request for Electric Service. Georgia Power's own reports count only projects that have executed a Request for Electric Service or a Contract for Electric Service as customer commitments, and this page uses the same line. A pipeline total is the sum of what projects have asked about, not a forecast of demand.
The segment column ("Data Center", "Manufacturing", "Clean Energy Tech") is Georgia Power's label, not this site's. Its wording changed between quarters ("Data Centers", "Data Center", "Data Center/Crypto"), and the labels are shown as filed rather than merged.
A removed project left the report; it did not necessarily stop. The reasons are Georgia Power's, quoted as filed. One of them ("See Note 1") says the project is still active but its load is now below the large-load threshold. A removal says nothing about what can now be connected anywhere.
What changed in Q2 2026
From Georgia Power's own lists, against Q1 2026: 11 projects added (6,776 MW), 6 removed from the report (1,382 MW), 6 with a restated load (net +1,535 MW), 1 stage change and 10 changes to an initial in-service date. These add up: 73,130 MW last quarter, plus 6,776 added, minus 1,382 removed, plus 1,535 restated, is 80,059 MW.
Added
| Announced MW | Entered the pipeline |
|---|---|
| 1,500 | June 11, 2026 |
| 900 | June 30, 2026 |
| 880 | June 17, 2026 |
| 750 | May 1, 2026 |
| 700 | June 2, 2026 |
| 612 | June 30, 2026 |
| 534 | May 7, 2026 |
| 400 | May 11, 2026 |
| 200 | May 6, 2026 |
| 200 | June 30, 2026 |
| 100 | April 21, 2026 |
Removed from the report
| Announced MW last quarter | Reason, as filed |
|---|---|
| 450 | No Decision |
| 405 | See Note 1 “Project still active but load now falls below the threshhold to be a large load customer” |
| 252 | See Note 1 “Project still active but load now falls below the threshhold to be a large load customer” |
| 180 | See Note 1 “Project still active but load now falls below the threshhold to be a large load customer” |
| 50 | Site |
| 45 | See Note 1 “Project still active but load now falls below the threshhold to be a large load customer” |
Restated load
| Change | Last quarter | This quarter |
|---|---|---|
| +755 MW | 481 | 1,236 |
| +610 MW | 910 | 1,520 |
| +251 MW | 500 | 751 |
| +24 MW | 264 | 288 |
| +20 MW | 230 | 250 |
| −125 MW | 240 | 115 |
Stage changes
| From | To |
|---|---|
| Technical Review | Request for Electric Service |
A project removed from the report may still be active; the reason is Georgia Power's. A removal is not evidence that power can be connected anywhere.
Quarter by quarter
Every public quarter on file. Added, removed and restated are Georgia Power's own lists. "Adds up" means last quarter's total plus those lists equals this quarter's, to the megawatt and the project.
| Quarter | Projects | Announced | Request or Contract | Added | Removed | Restated | Adds up? | Filing |
|---|---|---|---|---|---|---|---|---|
| Q2 2026 | 118 | 80.1 GW | 32 · 15.6 GW | 11 · 6,776 MW | 6 · 1,382 MW | +1,535 MW | Yes | filed August 17, 2026 |
| Q1 2026 | 113 | 73.1 GW | 31 · 12.4 GW | 13 · 12,626 MW | 6 · 2,850 MW | −2,518 MW | Yes | filed May 15, 2026 |
| Q4 2025 | 106 | 65.9 GW | 29 · 11.8 GW | 22 · 23,035 MW | 23 · 7,281 MW | −745 MW | Yes | filed March 4, 2026 revised filing; replaces the one filed February 11, 2026 |
| Q3 2025 | 107 | 50.9 GW | 28 · 11.0 GW | 13 · 6,780 MW | 24 · 14,345 MW | +1,606 MW | Yes | filed March 4, 2026 revised filing; replaces the one filed November 21, 2025 |
| Q2 2025 | 118 | 56.8 GW | 26 · 8.8 GW | 11 · 5,990 MW | 8 · 1,636 MW | +375 MW | Yes | filed August 15, 2025 |
| Q1 2025 | 115 | 52.1 GW | 26 · 8.3 GW | 19 · 10,571 MW | 8 · 2,291 MW | −367 MW | Yes | filed May 22, 2025 |
| Q4 2024 | 104 | 44.2 GW | 26 · 8.3 GW | 18 · 12,203 MW | 4 · 1,698 MW | −957 MW | Yes | filed February 21, 2025 |
| Q3 2024 | 90 | 34.6 GW | 25 · 8.0 GW | 30 · 14,737 MW | 10 · 3,002 MW | +134 MW | Yes | filed November 18, 2024 |
| Q2 2024 | 70 | 22.8 GW | 24 · 7.3 GW | not listed | 10 · 2,595 MW | −581 MW | Not checkable* | filed August 16, 2024 |
| Q1 2024 | 64 | 19.6 GW | 23 · 6.2 GW | not listed | 20 · 6,080 MW | −204 MW | First public quarter | filed May 15, 2024 |
* Q2 2024 has no list of added projects, so it cannot be checked against Q1 2024. To add up, it would need 16 added projects totaling 6,359 MW that Georgia Power did not itemize.
Projects in Q2 2026
All 118 rows, largest announced load first. Contract for Electric Service: 22 (9.6 GW) · Request for Electric Service: 10 (6.0 GW) · Technical Review: 86 (64.5 GW). Announced load is what Georgia Power reports for the project as of 2037, not a study result and not a commitment.
| Announced MW | Stage | Segment, as filed | Territory | Initial in-service |
|---|---|---|---|---|
| 3,500 | Technical Review | Data Center/Crypto | Inside | Q2 2031 |
| 3,210 | Request for Electric Service | Data Center/Crypto | Inside | Q2 2028 |
| 3,000 | Technical Review | Data Center/Crypto | Outside | Q4 2027 |
| 2,000 | Technical Review | Data Center/Crypto | Outside | Q2 2028 |
| 2,000 | Technical Review | Data Center/Crypto | Outside | Q2 2028 |
| 2,000 | Technical Review | Data Center/Crypto | Outside | Q2 2028 |
| 1,600 | Technical Review | Data Center/Crypto | Inside | Q2 2030 |
| 1,520 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 1,500 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 1,500 | Technical Review | Data Center/Crypto | Outside | Q2 2028 |
| 1,463 | Technical Review | Data Center/Crypto | Outside | Q4 2027 |
| 1,429 | Contract for Electric Service | Data Center/Crypto | Outside | Q2 2024 |
| 1,400 | Contract for Electric Service | Data Center/Crypto | Inside | Q4 2027 |
| 1,400 | Contract for Electric Service | Data Center/Crypto | Inside | Q2 2028 |
| 1,400 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 1,400 | Technical Review | Data Center/Crypto | Inside | Q2 2030 |
| 1,236 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 1,200 | Technical Review | Data Center/Crypto | Outside | Q2 2028 |
| 1,200 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 1,200 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 1,200 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 1,200 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 1,200 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 1,115 | Technical Review | Data Center/Crypto | Outside | Q2 2028 |
| 1,020 | Technical Review | Manufacturing | Multiple Sites | Q4 2027 |
| 1,000 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 910 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 910 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 901 | Contract for Electric Service | Data Center/Crypto | Inside | Q4 2027 |
| 900 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 880 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 860 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 840 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 800 | Contract for Electric Service | Data Center/Crypto | Inside | Q1 2027 |
| 751 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 750 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 750 | Technical Review | Data Center/Crypto | Outside | Q2 2028 |
| 725 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 725 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 700 | Technical Review | Data Center/Crypto | Outside | Q4 2027 |
| 693 | Request for Electric Service | Data Center/Crypto | Inside | Q2 2028 |
| 651 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 648 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 648 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 612 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 600 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 600 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 600 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 600 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 576 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 567 | Technical Review | Data Center/Crypto | Inside | Q2 2030 |
| 550 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 550 | Technical Review | Data Center/Crypto | Outside | Q2 2030 |
| 550 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 534 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 523 | Contract for Electric Service | Data Center/Crypto | Outside | Q4 2026 |
| 502 | Request for Electric Service | Data Center/Crypto | Inside | Q2 2028 |
| 500 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 500 | Technical Review | Data Center/Crypto | Inside | Q2 2030 |
| 500 | Technical Review | Manufacturing | Inside | Q4 2027 |
| 480 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 455 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 455 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 455 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 455 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 450 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 450 | Technical Review | Data Center/Crypto | Outside | Q4 2027 |
| 432 | Request for Electric Service | Data Center/Crypto | Inside | Q2 2029 |
| 432 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 420 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 400 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 365 | Technical Review | Data Center/Crypto | Outside | Q4 2027 |
| 365 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 360 | Technical Review | Data Center/Crypto | Outside | Q4 2027 |
| 360 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 350 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 350 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 325 | Technical Review | Data Center/Crypto | Outside | Q2 2028 |
| 324 | Contract for Electric Service | Data Center/Crypto | Inside | Q2 2026 |
| 311 | Contract for Electric Service | Data Center/Crypto | Inside | Q1 2026 |
| 300 | Request for Electric Service | Data Center/Crypto | Inside | Q2 2028 |
| 300 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 300 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 288 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 250 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 250 | Technical Review | Data Center/Crypto | Outside | Q4 2027 |
| 240 | Contract for Electric Service | Data Center/Crypto | Inside | Q1 2025 |
| 240 | Contract for Electric Service | Data Center/Crypto | Outside | Q4 2025 |
| 240 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 233 | Request for Electric Service | Data Center/Crypto | Inside | Q2 2030 |
| 225 | Request for Electric Service | Data Center/Crypto | Inside | Q2 2028 |
| 216 | Contract for Electric Service | Data Center/Crypto | Inside | Q1 2028 |
| 216 | Contract for Electric Service | Data Center/Crypto | Inside | Q3 2025 |
| 216 | Request for Electric Service | Data Center/Crypto | Inside | Q2 2030 |
| 216 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 216 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 207 | Contract for Electric Service | Clean Energy Tech | Outside | Q4 2025 |
| 200 | Technical Review | Data Center/Crypto | Outside | Q4 2027 |
| 200 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 200 | Technical Review | Data Center/Crypto | Outside | Q4 2027 |
| 200 | Technical Review | Data Center/Crypto | Inside | Q4 2027 |
| 192 | Contract for Electric Service | Data Center/Crypto | Outside | Q1 2024 |
| 182 | Contract for Electric Service | Data Center/Crypto | Inside | Q2 2026 |
| 180 | Contract for Electric Service | Data Center/Crypto | Outside | Q1 2026 |
| 180 | Contract for Electric Service | Data Center/Crypto | Inside | Q4 2026 |
| 180 | Technical Review | Data Center/Crypto | Inside | Q2 2029 |
| 175 | Technical Review | Data Center/Crypto | Inside | Q2 2028 |
| 150 | Contract for Electric Service | Data Center/Crypto | Inside | Q4 2024 |
| 145 | Contract for Electric Service | Data Center/Crypto | Inside | Q4 2028 |
| 144 | Technical Review | Data Center/Crypto | Outside | Q2 2029 |
| 126 | Contract for Electric Service | Clean Energy Tech | Inside | Q4 2025 |
| 120 | Contract for Electric Service | Data Center/Crypto | Inside | Q3 2026 |
| 115 | Technical Review | Clean Energy Tech | Inside | Q4 2027 |
| 105 | Request for Electric Service | Manufacturing | Inside | Q4 2027 |
| 100 | Technical Review | Manufacturing | Economic Development | Q2 2030 |
| 90 | Contract for Electric Service | Clean Energy Tech | Inside | Q4 2025 |
| 79 | Request for Electric Service | Manufacturing | Outside | Q4 2027 |
| 50 | Technical Review | Manufacturing | Inside | Q2 2030 |
Source
Georgia Power Company, Quarterly Large Load Economic Development Report, public-disclosure attachment, Georgia Public Service Commission
Docket 55378
(the reports also cite Docket 56002). Q2 2026 report
filed August 17, 2026; workbook PD Large Load Economic Development Report Q2 2026.xlsx.
Retrieved 2026-10-24; exported 2026-11-23.
- Project name, city, county and GPS coordinates are redacted in the public version, so no row can be located or followed from one quarter to the next.
- Announced load is the load Georgia Power reports for each project as of 2037, from its economic development pipeline. It is not a study result or a commitment.
- Changes are Georgia Power's own quarter-over-quarter lists, reproduced as filed. They are not computed by Substation Scout.
- Segment labels are Georgia Power's, and they changed between quarters ("Data Centers", "Data Center", "Data Center/Crypto"). They are shown as filed, not merged.
- The Q1 and Q2 2024 attachments have no list of added projects, so those quarters cannot be checked against the one before.