Tap Krum West Swtich - Riley7B substation interconnection queue
2 active projects totalling 181.9 MW in the ERCOT queue.
2active projects
181.9active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 25INR0154 | Nymphaea Solar | 345 | 120.9 | Solar | SS Completed, FIS Started, IA |
| 25INR0155 | Nymphaea Storage | 345 | 61 | Battery | SS Completed, FIS Started, IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.