Blackwater substation interconnection queue

2 active projects totalling 814.5 MW in the ERCOT queue.

2active projects
814.5active MW
2total filed
Queue IDProjectkVMWResourceStatus
22INR0462 Old Aqueduct Solar 345 511.6 Solar SS Completed, FIS Started, No IA
22INR0330 Old Aqueduct Batt 345 302.9 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.