Wheeler, TX interconnection queue

1 active project totalling 1,300 MW in the ERCOT queue.

1active projects
1,300active MW
1total filed
Queue IDProjectkVMWResourceStatus
30INR0077 Moon Hammer 345 1,300 Gas SS Completed, FIS Started, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.