Van Zandt, TX interconnection queue

8 active projects totalling 986.2 MW in the ERCOT queue.

8active projects
986.2active MW
8total filed
Queue IDProjectkVMWResourceStatus
25INR0253 Whiskey BESS 138 153.7 Battery SS Completed, FIS Completed, IA
25INR0384 Zorro BESS 138 153.7 Battery SS Completed, FIS Completed, IA
26INR0253 Goldfinch Solar n/r 150.8 Solar SS Completed, FIS Started, No IA
23INR0045 Caney Creek Solar 138 121 Solar SS Completed, FIS Started, IA
24INR0472 Amador Storage 138 102.4 Battery SS Completed, FIS Completed, IA
27INR0317 Edgewood BESS 1 138 102.1 Battery SS Completed, FIS Started, No IA
27INR0413 Edgewood BESS 2 138 102.1 Battery SS Completed, FIS Started, No IA
26INR0254 Goldfinch Storage n/r 100.4 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.