Throckmorton, TX interconnection queue
6 active projects totalling 960.6 MW in the ERCOT queue, plus 2 with terminal status (shown greyed).
6active projects
960.6active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 21INR0263 | Monarch Creek Wind | 345 | 283.4 | Wind | SS Completed, FIS Completed, IA |
| 26INR0316 | Lonesome Dove BESS | n/r | 256.1 | Battery | Inactive |
| 26INR0326 | Leaning Tree BESS | n/r | 256.1 | Battery | Inactive |
| 30INR0123 | Sideoats Solar 1 | 345 | 167.6 | Solar | SS Started, FIS Started, No IA |
| 30INR0124 | Sideoats Solar 2 | 345 | 167.6 | Solar | SS Started, FIS Started, No IA |
| 30INR0125 | Sideoats Solar 3 | 345 | 167.6 | Solar | SS Started, FIS Started, No IA |
| 26INR0327 | Sleepy Hollow BESS | 138 | 123.1 | Battery | SS Completed, FIS Completed, No IA |
| 25INR0558 | Ayass BESS | 69 | 51.3 | Battery | SS Completed, FIS Started, No IA |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.