Substation Scout

Stephens, TX interconnection queue

3 active projects totalling 301.4 MW in the ERCOT queue.

3active projects
301.4active MW
3total filed
Queue IDProjectkVMWResourceStatus
21INR0240 La Casa Wind 138 148.4 Wind SS Completed, FIS Completed, IA
26INR0600 Crocus Solar 138 102 Solar SS Completed, FIS Started, No IA
26INR0601 Crocus Storage 138 51 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.