Roberts, TX interconnection queue

1 active project totalling 250.7 MW in the ERCOT queue.

1active projects
250.7active MW
1total filed
Queue IDProjectkVMWResourceStatus
29INR0341 Pampa Natural Gas n/r 250.7 Gas SS Started, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.