Lubbock, TX interconnection queue

1 active project totalling 226.3 MW in the ERCOT queue, plus 4 with terminal status (shown greyed).

1active projects
226.3active MW
5total filed
Queue IDProjectkVMWResourceStatus
25INR0313 Staked Plains BESS n/r 254.8 Battery Inactive
23INR0310 Dunkel BESS 115 226.3 Battery SS Completed, FIS Started, No IA
21INR0202 R Massengale n/r 58 Gas Inactive
21INR0506 Ty Cooke n/r 33 Gas Inactive
21INR0201 Brandon n/r 21 Gas Inactive

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.