Knox, TX interconnection queue

8 active projects totalling 1,860.9 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

8active projects
1,860.9active MW
9total filed
Queue IDProjectkVMWResourceStatus
28INR0008 Oriole Solar 345 503.9 Solar SS Completed, FIS Started, IA
24INR0258 Zeissel Solar 345 451.5 Solar SS Completed, FIS Started, IA
26INR0531 West Munday Wind 345 351.9 Wind SS Completed, FIS Started, IA
29INR0122 Sundance Solar n/r 301 Solar Inactive
28INR0206 Wagon Timber Solar 138 172.1 Solar SS Completed, FIS Started, No IA
28INR0009 Oriole BES 345 150.4 Battery SS Completed, FIS Started, IA
26INR0112 Lemma Solar 138 100.6 Solar SS Completed, FIS Started, No IA
26INR0617 Knox County Moore Storage 138 77 Battery SS Completed, FIS Started, No IA
28INR0207 Wagon Timber Storage 138 53.5 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.