Kenedy, TX interconnection queue

4 active projects totalling 1,310.6 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

4active projects
1,310.6active MW
5total filed
Queue IDProjectkVMWResourceStatus
27INR0310 Tall Saddle Wind 345 522.8 Wind SS Completed, FIS Started, No IA
28INR0180 Green Ocelot Solar 345 357 Solar SS Completed, FIS Started, No IA
27INR0309 Tall Saddle Solar 345 252.3 Solar SS Completed, FIS Started, No IA
20INR0043 Gulf Wind 2 n/r 226.5 Wind Inactive
28INR0189 Green Ocelot Storage 345 178.5 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.