Substation Scout

Kenedy, TX interconnection queue

4 active projects totalling 1,310.6 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

4active projects
1,310.6active MW
5total filed
Queue IDProjectkVMWResourceStatus
27INR0310 Tall Saddle Wind 345 522.8 Wind SS Completed, FIS Started, No IA
28INR0180 Green Ocelot Solar 345 357 Solar SS Completed, FIS Completed, No IA
27INR0309 Tall Saddle Solar 345 252.3 Solar SS Completed, FIS Started, No IA
20INR0043 Gulf Wind 2 n/r 226.5 Wind Inactive
28INR0189 Green Ocelot Storage 345 178.5 Battery SS Completed, FIS Completed, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.