Substation Scout

Irion, TX interconnection queue

1 active project totalling 150 MW in the ERCOT queue.

1active projects
150active MW
1total filed
Queue IDProjectkVMWResourceStatus
29INR0356 Enfinity Cedar 138 150 Battery SS Started, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.