Hardeman, TX interconnection queue
8 active projects totalling 2,193.8 MW in the ERCOT queue.
8active projects
2,193.8active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 23INR0055 | Tabor Solar | 345 | 506.4 | Solar | SS Completed, FIS Started, No IA |
| 23INR0233 | Earthwise Solar | 345 | 370.5 | Solar | SS Completed, FIS Started, No IA |
| 26INR0171 | Lazy U Solar 1 | 345 | 252 | Solar | SS Completed, FIS Started, No IA |
| 26INR0172 | Lazy U Solar 2 | 345 | 252 | Solar | SS Completed, FIS Started, No IA |
| 26INR0173 | Juniper Ridge BESS 1 | 345 | 251.5 | Battery | SS Completed, FIS Started, No IA |
| 26INR0174 | Juniper Ridge BESS 2 | n/r | 251.5 | Battery | SS Completed, FIS Started, No IA |
| 27INR0063 | Supra Wind | 345 | 205.9 | Wind | SS Completed, FIS Started, No IA |
| 26INR0496 | Hardeman BESS | 138 | 104 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.