Queue IDProjectkVMWResourceStatus
23INR0055 Tabor Solar 345 506.4 Solar SS Completed, FIS Started, No IA
23INR0233 Earthwise Solar 345 370.5 Solar SS Completed, FIS Started, No IA
26INR0171 Lazy U Solar 1 345 252 Solar SS Completed, FIS Started, No IA
26INR0172 Lazy U Solar 2 345 252 Solar SS Completed, FIS Started, No IA
26INR0173 Juniper Ridge BESS 1 345 251.5 Battery SS Completed, FIS Started, No IA
26INR0174 Juniper Ridge BESS 2 n/r 251.5 Battery SS Completed, FIS Started, No IA
27INR0063 Supra Wind 345 205.9 Wind SS Completed, FIS Started, No IA
26INR0496 Hardeman BESS 138 104 Battery SS Completed, FIS Started, No IA