Substation Scout

Erath, TX interconnection queue

3 active projects totalling 664.6 MW in the ERCOT queue.

3active projects
664.6active MW
3total filed
Queue IDProjectkVMWResourceStatus
25INR0661 McCrae Energy Storage 345 306.4 Battery SS Completed, FIS Completed, IA
23INR0202 Erath County Solar 345 207.4 Solar SS Completed, FIS Started, IA
28INR0290 Field Marshal Storage 138 150.8 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.