DeWitt, TX interconnection queue

5 active projects totalling 971.9 MW in the ERCOT queue, plus 2 with terminal status (shown greyed).

5active projects
971.9active MW
7total filed
Queue IDProjectkVMWResourceStatus
23INR0282 BAYSIDE II SOLAR n/r 252.8 Solar Inactive
24INR0236 Bayside 2 BESS n/r 252.3 Battery Inactive
24INR0555 Shaula I BESS 345 205.8 Battery SS Completed, FIS Started, No IA
22INR0251 Shaula I Solar 345 205.2 Solar SS Completed, FIS Started, IA
22INR0267 Shaula II Solar 345 205.2 Solar SS Completed, FIS Started, IA
23INR0009 Shaula III Solar 345 205.2 Solar SS Completed, FIS Started, No IA
26INR0328 Yorktown BESS 138 150.5 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.