Cooke, TX interconnection queue
5 active projects totalling 947.8 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).
5active projects
947.8active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 24INR0198 | Two Forks BESS | 138 | 309.8 | Battery | SS Completed, FIS Started, IA |
| 28INR0328 | 18-ALPHA BESS | 138 | 307.4 | Battery | SS Completed, FIS Started, No IA |
| 26INR0598 | Tennuto BESS | n/r | 202 | Battery | Cancelled |
| 20INR0033 | WILDWIND | 345 | 180.1 | Wind | SS Completed, FIS Completed, IA |
| 26INR0219 | Mountain Springs BESS | 138 | 150.5 | Battery | SS Completed, FIS Completed, No IA |
| 24INR0239 | Trojan BESS SLF | 345 | 0 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.