Castro, TX interconnection queue
7 active projects totalling 2,303.6 MW in the ERCOT queue, plus 2 with terminal status (shown greyed).
7active projects
2,303.6active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 29INR0035 | Cavell Wind | 345 | 641.2 | Wind | SS Completed, FIS Started, No IA |
| 29INR0034 | Cavell Solar | 345 | 502.1 | Solar | SS Completed, FIS Started, No IA |
| 25INR0460 | Acker BESS | 345 | 301 | Battery | SS Completed, FIS Completed, IA |
| 19INR0175 | Shifting Gale Wind | n/r | 289 | Wind | Inactive |
| 27INR0143 | Ogalalla Storage | 345 | 251.6 | Battery | SS Completed, FIS Started, No IA |
| 20INR0050 | Castro Solar | 345 | 224.7 | Solar | SS Completed, FIS Started, IA |
| 16INR0049 | Nazareth Solar | 345 | 203 | Solar | SS Completed, FIS Completed, IA |
| 23INR0015 | Scarlet Solar | 345 | 180 | Solar | SS Completed, FIS Started, No IA |
| 16INR0033 | Hart Wind (Old POI) | n/r | 165 | Wind | Inactive |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.