Burnet, TX interconnection queue

4 active projects totalling 394.7 MW in the ERCOT queue.

4active projects
394.7active MW
4total filed
Queue IDProjectkVMWResourceStatus
24INR0313 Backbone Creek BESS 138 124.1 Battery SS Completed, FIS Completed, IA
26INR0499 Mineral Springs BESS 138 104 Battery SS Completed, FIS Started, No IA
27INR0125 RedSun BESS n/r 84 Battery SS Completed, FIS Completed, No IA
27INR0124 RedSun Solar 138 82.6 Solar SS Completed, FIS Completed, IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.