Briscoe, TX interconnection queue

4 active projects totalling 1,964.4 MW in the ERCOT queue.

4active projects
1,964.4active MW
4total filed
Queue IDProjectkVMWResourceStatus
29INR0031 Commodus Wind 345 641.4 Wind SS Completed, FIS Started, No IA
29INR0030 Commodus Solar 345 502.1 Solar SS Completed, FIS Started, No IA
23INR0330 BRP Snowdon BESS 345 410.9 Battery SS Completed, FIS Started, No IA
28INR0023 Silverton Solar 345 410 Solar SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.