Citrus Combined Cycle Substation substation interconnection queue

4 active projects totaling 2,153.9 MW in the Duke Energy queue, plus 1 with terminal status (shown grayed).

5 Duke Energy queue filings name Citrus Combined Cycle Substation as the point of interconnection, all in Citrus County, FL.

4active projects
2,153.9active MW
5total filed
Queue IDProjectkVMWResourceStatus
123 Not reported n/r 940 Gas Operational
124 Not reported n/r 940 Gas Operational
FC100380 Not reported 230 199 Battery Active
199 Not reported n/r 74.9 Solar Operational
234 Not reported n/r 74.9 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.