Home / Duke Energy / Substations / Asheville Energy Complex Switchyard; Asheville Plant
Asheville Energy Complex Switchyard; Asheville Plant substation interconnection queue
2 active projects
totaling 560 MW in the Duke Energy queue, plus 2 with terminal status (shown grayed).
4 Duke Energy queue filings name Asheville Energy Complex Switchyard; Asheville Plant as the point of interconnection, all in Buncombe County, NC.
2 active projects
560 active MW
4 total filed
Queue ID Project kV MW Resource Status
8599
Not reported
115
470
Gas
Withdrawn
8597
Not reported
115
280
Gas
Operational
8598
Not reported
230
280
Gas
Operational
8600
Not reported
230
280
Gas
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with Duke Energy before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, newer substations HIFLD lacks from OpenStreetMap, EIA gas transmission pipelines, HIFLD gas facilities and gas
utility territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.