Substation Scout

Duke Energy request PP00013

Duke Energy queue ID PP00013

Queue request PP00013 was listed in the Duke Energy interconnection queue at the end of 2025 as a 46.8 MW gas project in Richmond County, NC, according to Berkeley Lab’s queue data file. The filing names Smith as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 12, 2025.

Queue IDPP00013
Project nameNot reported
Status (as published)Active
SubstationSmith
Point of interconnectionSmith
CountyRichmond
StateNC
VoltageNot reported
Capacity46.8 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2025-11-12
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Smith substation: 2 requests in the Duke Energy queue, 2 active totaling 81.8 MW.

Queue IDProjectMWResourceStatus
PP00014Not reported35GasActive

Richmond, NC: 22 requests in the Duke Energy queue, 13 active totaling 1,106.6 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Progress
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Provisional GIA Executed
Queue date2025-04-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner