Montgomery, NC interconnection queue

3 active projects totaling 18.9 MW in the Duke Energy queue, plus 7 with terminal status (shown grayed).

3active projects
18.9active MW
10total filed
Queue IDProjectkVMWResourceStatus
169712 Not reported 230 80 Solar Withdrawn
567240 Not reported 230 75 Solar Withdrawn
569168 Not reported 115 75 Solar Withdrawn
890907 Not reported 115 75 Solar Withdrawn
920545 Not reported n/r 75 Solar Withdrawn
5703 Not reported 115 70.2 Solar Withdrawn
890837 Not reported 230 70 Solar Withdrawn
PP00033 Not reported n/r 6.3 Hydro Active
570430 Not reported n/r 6.3 Hydro Active
899433 Not reported n/r 6.3 Hydro Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.