Substation Scout

Florence, SC interconnection queue

6 active projects totaling 94.5 MW in the Duke Energy queue, plus 11 with terminal status (shown grayed).

6active projects
94.5active MW
17total filed
Queue IDProjectkVMWResourceStatus
22136 Not reported 115 75.5 Solar Withdrawn
19397 Not reported 115 75 Solar Withdrawn
915787 Not reported 230 65 Solar Active
PP00031 Not reported n/r 65 Other Withdrawn
4598 Not reported 230 10 Solar Withdrawn
4697 Not reported 230 10 Solar Withdrawn
4698 Not reported 230 10 Solar Withdrawn
4703 Not reported 230 10 Solar Withdrawn
4732 Not reported 230 10 Solar Withdrawn
4741 Not reported 230 10 Solar Withdrawn
7638 Not reported 230 10 Solar Withdrawn
8615 Not reported 115 10 Other Operational
977864 Not reported 230 5 Solar Active
977879 Not reported 115 5 Solar Active
898329 Not reported n/r 5 Solar Withdrawn
957087 Not reported 230 5 Solar Active
956532 Not reported 230 4.5 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.