Home / BPA / county / Tillamook, OR
Tillamook, OR interconnection queue
3 active projects
totalling 4 MW in the BPA queue.
3 active projects
4 active MW
3 total filed
Queue ID Project kV MW Resource Status
G0480
G0480 Port of Tillamook Bay Gas Digester Project
n/r
2
Other
ENERGIZED
G0449
Farm Power Misty Meadow
n/r
1
Other
ENERGIZED
G0450
Farm Power Tillamook
n/r
1
Other
ENERGIZED
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with BPA before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.