0 active projects totalling 0 MW in the BPA queue, plus 4 with terminal status (shown greyed).

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatus
G0749 Not reported 230 300 Solar WITHDRAWN
G0857 Not reported n/r 300 Wind WITHDRAWN
G0856 Not reported n/r 220 Battery WITHDRAWN
G0720 Not reported 230 120 Battery WITHDRAWN

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.