Substation Scout

Marion, OR interconnection queue

1 active project totalling 1 MW in the BPA queue, plus 2 with terminal status (shown greyed).

1active projects
1active MW
3total filed
Queue IDProjectkVMWResourceStatus
G0754 Not reported 500 1,650 Solar WITHDRAWN
G83 Sempra Generation 500 612 Gas WITHDRAWN
G1066 Not reported 115 1 Solar BPA COMPLETED

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.