Lincoln, WA interconnection queue
4 active projects totalling 1,500 MW in the BPA queue, plus 4 with terminal status (shown greyed).
4active projects
1,500active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| G0953 | Not reported | n/r | 600 | Wind | STUDY |
| G0956 | Not reported | n/r | 400 | Wind | STUDY |
| G0954 | Not reported | n/r | 350 | Wind | WITHDRAWN |
| G0955 | Not reported | n/r | 350 | Wind | STUDY |
| G0860 | Not reported | 230 | 300 | Wind | WITHDRAWN |
| G0997 | Not reported | 115 | 300 | Wind | WITHDRAWN |
| G0985 | Not reported | 115 | 150 | Solar | STUDY |
| G0210 | Not reported | 115 | 75 | Wind | WITHDRAWN |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.