Lewis, WA interconnection queue

2 active projects totalling 300 MW in the BPA queue, plus 10 with terminal status (shown greyed).

2active projects
300active MW
12total filed
Queue IDProjectkVMWResourceStatus
G9 1100MW Paul 500 1,100 Gas WITHDRAWN
G0595 Not reported 230 307 Wind WITHDRAWN
G1007 Not reported n/r 300 Battery STUDY
G20 Centralia Generation Addition 500 248 Gas Decommissioned (terminated)
G0769 Not reported 230 170 Wind WITHDRAWN
G0718 Not reported 230 160 Wind WITHDRAWN
G0315 Not reported 115 150 Wind WITHDRAWN
G0515 Not reported 230 150 Wind WITHDRAWN
G0313 Not reported n/r 128 Wind WITHDRAWN
G13 Centralia Generation 500 50 Gas Decommissioned (terminated)
G0482 Not reported n/r 1 Hydro WITHDRAWN
G1072 Not reported 500 0 Battery RECEIVED

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.