1 active project totalling 150 MW in the BPA queue, plus 2 with terminal status (shown greyed).

1active projects
150active MW
3total filed
Queue IDProjectkVMWResourceStatus
G55 Cedar Hills Energy LLC 230 300 Gas WITHDRAWN
G89 Enron Power Marketing 230 300 Gas WITHDRAWN
G1014 Not reported n/r 150 Battery STUDY

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.