APS request Q493

APS queue ID Q493

Queue request Q493 was listed in the APS interconnection queue at the end of 2025 as a 100 MW hybrid project in Pinal County, AZ, according to Berkeley Lab’s queue data file. The filing names Milligan Switchyard as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of January 15, 2025.

Queue IDQ493
Project nameNot reported
Status (as published)Active
SubstationMilligan Switchyard
Point of interconnectionMilligan Switchyard 69 kV
CountyPinal
StateAZ
Voltage69 kV
Capacity100 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2025-01-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Pinal, AZ: 80 requests in the APS queue, 27 active totaling 5,881.9 MW.

Tracked changes

Not tracked. APS rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityArizona Public Service
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Transitional Cluster: Cluster Study (Phase 2)
Queue date2023-02-13
Components (hybrid)Solar 100 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first