Raccoon Mountain 161-kV Substation substation interconnection queue

4 active projects totaling 76 MW in the TVA queue.

4 TVA queue filings name Raccoon Mountain 161-kV Substation as the point of interconnection, all in Marion County, TN.

4active projects
76active MW
4total filed
Queue IDProjectkVMWResourceStatus
322 Not reported n/r 27 Hydro Active
323 Not reported n/r 27 Hydro Active
320 Not reported n/r 11 Hydro Active
321 Not reported n/r 11 Hydro Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.