TVA request 672

TVA queue ID 672

Queue request 672 was listed in the TVA interconnection queue at the end of 2025 as a 140 MW solar project in Rankin County, MS, according to Berkeley Lab’s queue data file. The filing names TVA's Sebastopol-Leake TL as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 1, 2027.

Queue ID672
Project nameNot reported
Status (as published)Active
SubstationTVA's Sebastopol-Leake TL
Point of interconnectionTVA's Sebastopol-Leake 161kV TL
CountyRankin
StateMS
Voltage161 kV
Capacity140 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2027-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Rankin, MS: 3 requests in the TVA queue, 1 active totaling 140 MW.

Tracked changes

Not tracked. TVA rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityTennessee Valley Authority
ClusterTC25-069
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Queue date2024-10-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first