Queue request 672 was listed in the TVA interconnection queue at the end of 2025 as a 140 MW solar project in Rankin County, MS, according to Berkeley Lab’s queue data file. The filing names TVA's Sebastopol-Leake TL as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 1, 2027.
| Queue ID | 672 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | TVA's Sebastopol-Leake TL |
| Point of interconnection | TVA's Sebastopol-Leake 161kV TL |
| County | Rankin |
| State | MS |
| Voltage | 161 kV |
| Capacity | 140 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2027-09-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Rankin, MS: 3 requests in the TVA queue, 1 active totaling 140 MW.
Tracked changes
Not tracked. TVA rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Tennessee Valley Authority |
|---|---|
| Cluster | TC25-069 |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Cluster Study |
| Queue date | 2024-10-30 |