TVA request 611
TVA queue ID 611
Queue request 611 was listed in the TVA interconnection queue at the end of 2025 as a 100 MW solar project in Maury County, TN, according to Berkeley Lab’s queue data file. The filing names Mt. Pleasant substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 15, 2027.
| Queue ID | 611 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Mt. Pleasant substation |
| Point of interconnection | Mt. Pleasant 161kV substation |
| County | Maury |
| State | TN |
| Voltage | 161 kV |
| Capacity | 100 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2027-04-15 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Maury, TN: 14 requests in the TVA queue, 1 active totaling 100 MW.
Tracked changes
Not tracked. TVA rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Tennessee Valley Authority |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Facility Study |
| Queue date | 2024-03-25 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.