TVA request 482
TVA queue ID 482
Queue request 482 was listed in the TVA interconnection queue at the end of 2025 as a 110 MW solar project in Cumberland County, TN, according to Berkeley Lab’s queue data file. The filing names Plateau 500-kV Substation (161-kV Interconnection) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 13, 2027.
| Queue ID | 482 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Plateau 500-kV Substation (161-kV Interconnection) |
| Point of interconnection | Plateau 500-kV Substation (161-kV Interconnection) |
| County | Cumberland |
| State | TN |
| Voltage | Not reported |
| Capacity | 110 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2027-09-13 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Cumberland, TN: 3 requests in the TVA queue, 1 active totaling 110 MW.
Tracked changes
Not tracked. TVA rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Tennessee Valley Authority |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Queue date | 2021-10-05 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.