Substation Scout

TVA request 417

TVA queue ID 417

Queue request 417 was listed in the TVA interconnection queue at the end of 2025 as a 780 MW gas project in Muhlenberg County, KY, according to Berkeley Lab’s queue data file. The filing names Paradise 500-kV Station as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2022.

Queue ID417
Project nameNot reported
Status (as published)Active
SubstationParadise 500-kV Station
Point of interconnectionParadise 500-kV Station
CountyMuhlenberg
StateKY
VoltageNot reported
Capacity780 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online date2022-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Muhlenberg, KY: 14 requests in the TVA queue, 10 active totaling 2,691 MW.

Tracked changes

Not tracked. TVA rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityTennessee Valley Authority
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2020-02-10

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first