TVA request 25RSC-010
TVA queue ID 25RSC-010
Queue request 25RSC-010 was listed in the TVA interconnection queue at the end of 2025 as a 140 MW hybrid project in Graves County, KY, according to Berkeley Lab’s queue data file. The filing names TVA's PARIS-MAYFIELD (from SEG5772-3 4/) TL as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of January 31, 2031.
| Queue ID | 25RSC-010 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | TVA's PARIS-MAYFIELD (from SEG5772-3 4/) TL |
| Point of interconnection | TVA's PARIS-MAYFIELD (from SEG5772-3 4/2004) 161kV TL |
| County | Graves |
| State | KY |
| Voltage | 161 kV |
| Capacity | 140 MW |
| Resource (as published) | Solar+Battery |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2031-01-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Graves, KY: 1 request in the TVA queue, 1 active totaling 140 MW.
Tracked changes
Not tracked. TVA rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Tennessee Valley Authority |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | In Progress (unknown study) |
| Queue date | 2025-08-01 |
| Components (hybrid) | Solar 140 MW + Battery |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.