Substation Scout

Lowndes, MS interconnection queue

12 active projects totaling 2,820 MW in the TVA queue, plus 21 with terminal status (shown grayed).

12active projects
2,820active MW
33total filed
Queue IDProjectkVMWResourceStatus
3 Not reported n/r 1,170 Other Withdrawn
53 Not reported n/r 900 Other Operational
71 Not reported n/r 800 Other Withdrawn
2 Not reported n/r 700 Other Withdrawn
569 Not reported 161 620 Gas Active
575 Not reported n/r 620 Gas Withdrawn
213 Not reported n/r 570 Gas Withdrawn
65 Not reported n/r 510 Other Withdrawn
651 Not reported n/r 500 Solar Withdrawn
15 Not reported n/r 450 Other Operational
604 Not reported n/r 224 Solar Withdrawn
25RSC-013 Not reported 500 200 Battery Active
421 Not reported n/r 200 Hybrid Withdrawn
325 Not reported n/r 150 Solar Withdrawn
449 Not reported n/r 140 Hybrid Withdrawn
446 Not reported n/r 127 Solar Withdrawn
223 Not reported n/r 122 Gas Operational
475 Not reported n/r 120 Hybrid Withdrawn
307 Not reported n/r 100 Solar Withdrawn
341 Not reported n/r 100 Solar Operational
377 Not reported n/r 100 Solar Operational
415 Not reported n/r 100 Solar Operational
447 Not reported n/r 100 Hybrid Withdrawn
285 Not reported n/r 80 Solar Withdrawn
310 Not reported n/r 78 Gas Operational
274 Not reported n/r 74 Solar Withdrawn
630 Not reported n/r 69 Solar Withdrawn
277 Not reported n/r 65 Solar Withdrawn
378 Not reported n/r 50 Solar Operational
379 Not reported n/r 50 Battery Operational
380 Not reported n/r 50 Battery Operational
400 Not reported n/r 20 Solar Withdrawn
157 Not reported n/r 12 Other Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.