Lake, TN interconnection queue
3 active projects totaling 177 MW in the TVA queue, plus 7 with terminal status (shown grayed).
3active projects
177active MW
10total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 371 | Not reported | n/r | 227 | Solar | Withdrawn |
| 653 | Not reported | n/r | 100 | Solar | Withdrawn |
| 292 | Not reported | n/r | 80 | Solar | Active |
| 260 | Not reported | n/r | 68 | Solar | Withdrawn |
| 338 | Not reported | n/r | 68 | Solar | Withdrawn |
| 430 | Not reported | n/r | 68 | Solar | Withdrawn |
| 299 | Not reported | n/r | 67 | Solar | Active |
| 337 | Not reported | n/r | 30 | Solar | Active |
| 435 | Not reported | n/r | 17 | Battery | Withdrawn |
| 473 | Not reported | n/r | 9 | Hybrid | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with TVA before relying on these figures.
Site Scanner