Litton
In a case before the Kentucky Public Service Commission, “Hebron to Oakbrook 138 kV transmission line project (Litton named as a separate project)” (case 2024-00158). The station's utility: Duke Energy Kentucky.
Described as new. The quoted wording calls this substation new. “supplied from the planned new Litton substation” — Duke Energy Kentucky application, Case 2024-00158, p.139 (case 2024-00158)
Also mentioned: “The Litton substation project is not included as part of the application as it” — Duke Energy Kentucky application, Case 2024-00158, p.140 (case 2024-00158)
Note. The Boutwell testimony in Duke Energy Kentucky's application says the 69 kV system has limited capacity for expected load growth in the region to be supplied from the planned new Litton substation, and that the Litton substation project is a separate standalone project whose transmission line component is significantly less than one mile. A study map in the application marks a proposed Litton substation near Litton Lane in Hebron. The application does not print its voltage, in-service date or county.
Note. The same sentence appears in the earlier applications for this line (Cases 2022-00364 and 2023-00239, both denied without prejudice). The Commission granted the Hebron - Oakbrook CPCN on 2024-10-25.
The case documents print no county for this substation, and none has been found printed for it elsewhere yet.
Source: Kentucky Public Service Commission case records (psc.ky.gov): 36 transmission and substation cases filed since 2022 read by hand, 20 documents cited. Latest document dated November 13, 2026; retrieved 2026-11-21; records reviewed by hand 2026-11-21.
Before relying on any of this
- These are the substations named in Kentucky Public Service Commission cases since 2022: a utility files for a certificate when it builds most new transmission. Smaller substations, and projects that need no certificate, are not in these cases.
- A county is shown where the case prints it for the station; otherwise it is left blank.
- An application describes what a utility asks to build. Where the Commission has ruled, the page says so; an in-service date is the one the documents print, not a construction schedule.