Westover

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
115kV in the quote
GTC, MEAGproject sponsor
2projects in the plan

Described as new. The quoted wording calls this substation new. “new 115kV stations, Lizard Lope and Westover” — TEAMS 18691, plan p.83

Note. Another project in the plan rebuilds an existing Slappey Drive – Westover 115kV line, so a Westover station may already exist and this may be a rebuild or a second station of the same name. The plan does not say which. “SLAPPEY DRIVE - WESTOVER 115kV LINE REBUILD” — TEAMS 11051

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
MEAG: SLAPPEY DRIVE - WESTOVER 115kV LINE REBUILD
Rebuild 2.92 miles from Slappey Drive to Albany #9 with 200C 1351 ACSS.
TEAMS 11051 · plan p.216 · zone 216
MEAG In the plan
p.16
Jun 1, 2029 No change SLAPPEY DRIVE, Westover
GTC: LIZARD LOPE - WESTOVER 115kV NEW LINE
Construct two new 115kV stations, Lizard Lope and Westover, and build a new 19.8 miles of 115kV line with 100C Drake 795 ACSR conductor from Lizard Lope to Gillionville substation with 100C Drake 795 ACSR conductor.
TEAMS 18691 · plan p.83 · zone 216
GTC In the plan
p.7
Mar 1, 2026 No change Gillionville, Lizard Lope, Westover

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.