Gillionville
Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GTCproject sponsor
1projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: LIZARD LOPE - WESTOVER 115kV NEW LINE Construct two new 115kV stations, Lizard Lope and Westover, and build a new 19.8 miles of 115kV line with 100C Drake 795 ACSR conductor from Lizard Lope to Gillionville substation with 100C Drake 795 ACSR conductor. TEAMS 18691 · plan p.83 · zone 216 |
GTC | In the plan p.7 |
Mar 1, 2026 | No change | Gillionville, Lizard Lope, Westover |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.